Milestones


Phase 1: Redevelopment of Block E

Special Function Rooms Conversion in Block H

April 2016 – August 2016

Vacate Existing Block E

September 2016 - December 2016

Demolish existing Block E

June 2017 - July 2017

Construct new Block E

August 2017 - August 2019


Phase 2: Construction of New Assembly Hall

Technical Feasibility Study (TFS) Approved

February 2014

Project code to be released by EDB

September 2014

Tender Invitation and Award

April to November 2015

Detail design approved

September 2016

Application for Capital Works Resource Allocation Exercise (CWRAE) 2016

September 2016

Re-application for Capital Works Resource Allocation Exercise (CWRAE) 2017

September 2017